Watch Out for Seal Coating
Proper maintenance of the neighborhood streets throughout Talega requires the seal coating of the streets every 3 to 5 years as necessary to extend the life. All streets are evaluated by a consultant every year and a seal coat is applied as necessary to approximately 25% of the community. This year the following neighborhoods will have their streets seal coated. The project will be carried out in four (4) phases, Starting on August 22nd and culminating on September 17th, weather permitting. The neighborhoods affected this year are: Portomarin, Sabella, Stella Mare Phase 1 – August 22 – August 27 Bella Vista, Solana & Trinidad Phase 2 – August 29 – September 3 Alta, Carrillon & Altura Phase 3 – September 6 – September 10 Alora, Cazadero & Lucia Phase 4 – September 12 – September 17 Watch for additional information in an E-Blast on Monday, August 15, 2022.
|